- One-week discovery sprint to identify the work, people & stages involved
- Setup Agile ways of working and identified four key streams of work:
- Requirements backlog creation
- UX & UI Design
- New hosting environments & Code base setup
- Content creation and cataloguing
- We planned 5 two-weeks sprints starting with detailed user stories creation, new information architecture and identifying a detailed sitemap
- Followed by key templates design, components and unique graphic assets
- Moving into Frontend development and backend integration as soon as the first batch of designs were ready
- Team worked very closely even though everyone was at home due to the pandemic
- The design to frontend dev and then backend integration of individual components worked seamlessly, and the team delivered more than the committed backlog in each sprint
- The last sprint was used to test & fine-tune completed templates and pages with final content on the new environment
- The new website Axi.com was launched a day before the brand launch date of 1st October in order to allow media to access the new website
- The brand launch with a major announcement of AxiCorp sponsoring Manchester City FC, driving large amount of traffic to the website